![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEg_39IeRaSfjJll6yLlbNgOI5-rWA1kCTb0M8vY6tSNhn9ylmLJlcadiD7ni9ShEZPlpvQUR0I5dxVi72u6QP-4tOGMbQZ2j0_8BgY9EuhY4onwN-55NscuTo0H-MIzbq8Ge7KE0UYexiI/s400/ACAD+plans.jpg)
Wednesday, June 4, 2008
Physical model of structural panels with UB rafters
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEg_39IeRaSfjJll6yLlbNgOI5-rWA1kCTb0M8vY6tSNhn9ylmLJlcadiD7ni9ShEZPlpvQUR0I5dxVi72u6QP-4tOGMbQZ2j0_8BgY9EuhY4onwN-55NscuTo0H-MIzbq8Ge7KE0UYexiI/s400/ACAD+plans.jpg)
Tuesday, June 3, 2008
Coen Pre Cast Factory site Visit
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjT7DE7GBQKHbrObEVoPmMUz1nifB1mJQOAeAe25EOMSRl6vy7Voztshyphenhyphen9nKY2WoXdIErfZKmdTz5Qn0QWwCPuW-NEhLkGqRsbA3gibQZmXahCmml1HerO2CdXoc8P2e5OzD9aMzBjZacI/s400/Picture3.jpg)
A ready mix truck will pour into the panel bed, covering the formwork, reinforced mesh and any additional inserts the cement. (Above)
Once the panel have been poured they are left in their panel beds over night, the next day they are moved to the storage racks in the warehouse. (Below)
Lifting inserts are casted into the panel and can be tied to the reinforced mesh. They allow for easy access to lift the panel safely.
Panels are lifted from their casting beds the day after they are poured. By this time they have reached a lifting strength on 25mpa and are then left placed in the rack for a minimum of 7 days to allow them to cure enough to take transport and erection stresses
Monday, June 2, 2008
Convenant College Gym Site Visit
The Franna crane slowly lowers the panel into position while the two ground workers guide it using a burke (large crowbar).
Prior to any panels being lifted on site all the panel locations are marked out on the strip footings, and location pins are drilled in.
Once the structural panels are inplace, they need to be braced and propped using cast-in inserts to the panel and a deadman cast in-ground concrete anchoring brace (nominated on shop drawings).
This is a compliance/delivery document that is unique to each panel, it must have the panel id no., the date poured, the weight and strength of the panel. The crane driver can not lift a panel without this 'birth certificate'.
Saturday, May 31, 2008
Atex Steel Site visit
These are the connection that are to be welded to the UB, also pictured is the engineers drawings which specify the location of the holes that need to be drilled.
Once completely assembled the beams are treated with Inorganic zinc silicate primer paint, to protect the steel from exposed environments.
Thursday, May 22, 2008
Denny Lascelles Refurbishment 2
Denny Lascelles Refurbishment
Wednesday, May 7, 2008
Warehouse Under Construction 2
Ridge connection with extensive haunching braced to 'c' purlins. There is safety mesh supporting the insulation, covered with Kliplok roofing, which you can see stack on the left ready to be fitted. Along with the red pipe, being the fire services.
The end wall panel shows the bracing from beams, which holds the individual smaller panels inplace. Along with the unfinished roof, hence the safety railing bolted to the 'c' purlins.