Joints & Connections

Here is a UB rafter at the knee joint, it also contains a cut UB haunch which are usually required for spans over 20 metres. This unified beam is supported by fly bracing to the 'C' purlins and it is also embedded in the brick pillar.
A standard four bolt cleat is used to connect the rafter and the purlins, in this instance it is replacing a knee joint and the haunch that is usually involved. In fact the majority of connections between the purlins and rafters were done using this technique.
This rigid connection using a cleat plate has allowed for extra bracing in two directions, with one member spanning between the central rafter and the exterior walls purlin and the other cross bracing to a 'c' purlin.

Load bearing brick pillars

The method of transferring the dead and wind loads from the roof downwards is done through the use of brick pillars, whereby the purlins and rafters are built into the brickwork where possible.
Here are two structural members braced together using cleats and two bolts, the rafter is then fixed into the solid brick wall.
This is an example of why portal frames with steel columns are now used, as you can see the purlins is just sitting on top of the brick ledge while the rafter appears to barely restrained by the degraded brickwork.
An extended view of one of the many brick pillars that support the beams and transfer all the loads into the ground.

1970's Portal Frame

This is a 1970's warehouse situated in Clayton, Melbourne. It is now home to a carpet warehouse and Floorworld retail showroom. An immediate difference to that of the design from Bunnings is the extensive use of bricks and windows.
As is evident by the state of the insultation this warehouse is aging. But the same principle still apply, with a long spanning rafters and purlins allowing for uninterupted access that a forklift requires. What is interesting about this design is the long span cross bracing between rafter members, but this is not consistent throughout the warehouse.
The warehouse bares a low pitching roof only spanning approximately 20 metres.

Wednesday, March 19, 2008

Sunday, March 16, 2008

Tuesday, March 11, 2008

Structural members

This is a column supporting a long spanning rafter, designed to reinforce the connection between the two UB beams at the ridge. Haunching as seen above is also used for this same purpose, and in this case is approximately 10-15% in length of the total rafter span.

On a closer view you can see that the two UB beams are connected by bolted end plates. Also in this photo the roofings insulation and safety mesh are apparent.

Fly bracing is used in long span construction to connect the rafter to the roof purlins, it allows for uniformity within the structure and are useful in the resistance of wind loading.